Can I find the assignee at a specific step in the workflow on Greenhopper?

In Greenhopper, is it possible to find all issues that were assigned to a specific user at a specific step in the work flow? We have a "testing" step, and I want to find all issues that we assigned to a specific user in that step. I have gone…
Niel de Wet
  • 6,210
  • 6
  • 50
  • 91
1
vote
1 answer

Can I create a separate curve for sub-tasks in a Burndown chart?

I would like to know if it is possible to create a separate curve for sub-tasks in the Hour Burndown chart. So we will have two curves in the chart - one for the standard issue types and the other just for their sub-tasks? Is this possible? If yes,…
Miretz
  • 134
  • 1
  • 10
1
vote
1 answer

JIRA / Greenhopper move subtasks when moving stories

If I have a bunch of subtasks in JIRA under a story, and I then mark the story (or Bug) as "resolved" (from In Progress), how can I make it mark all of the subtasks as resolved? Likewise, if I have a bunch of subtasks and I move the last one from In…
Jordan
  • 8,774
  • 8
  • 31
  • 45
1
vote
3 answers

JIRA/Greenhopper - Alter fields in the "Add Sub-task" form

In Greenhopper, when I am in the Task Board, I have parent tasks and click the gear icon -> Add Sub-Task. The form opens up to add sub-tasks, sub-features, whatever. Does anyone know if there is a way to configure what fields show up on this form…
Sean Adkinson
  • 7,869
  • 3
  • 39
  • 62
1
vote
1 answer

How to get story point estimate Jira plugin development

I am developing a Jira report plugin. I have gathered a list of Issues and I need to find somehow the initial storypoint estimate for each of them. There is a method in the Issue class named getEstimate() but it returns null even for estimated…
Ionut
  • 13
  • 5
1
vote
2 answers

Is there a way to link a subtask to 2 User stories in Jira GreenHopper?

I'd like to be able to link a subtask to 2 different user stories. Couldn't find any such option easily available in the config screens .. Any ideas?
akapulko2020
  • 1,001
  • 2
  • 19
  • 34
1
vote
2 answers

Is there a way to link group of issues to one issue in JIRA?

We would like to start using JIRA with GH for deployment/change management also. The proposed workflow for a Task/Story is as follows: Backlog -> Open (added in the Sprint) -> In progress (coding) -> Resolved (code committed, work done) -> To…
powpow
  • 147
  • 1
  • 2
  • 8
1
vote
1 answer

Adding a column to the task board

I've been given the admin task for our company Jira implementation. There has been zero handover from the previous guy which aint helpful. The previous guy had, in the Task Board, four columns; To Do In Progress To Verify Done Now I need to add…
griegs
  • 22,002
  • 28
  • 113
  • 201
1
vote
3 answers

How can I tell if I have GreenHopper installed on Jira?

I'm using Jira and have been told by the sysadmin that GreenHopper has been installed. However, I see no evidence that GreenHopper has been installed. Is there a simple way to determine whether or not GreenHopper has been installed?
user128807
  • 10,179
  • 16
  • 49
  • 72
1
vote
1 answer

Render Jira Agile Burndown in chartist.js?

Issue I'm using json data from jira to render a project's burndown chart. For reasons I won't go into, I can't use the built-in Jira Agile charts. I'm using chartist.js to render the burndown but I'm running into troubles and would appreciate a…
John Gordon
  • 2,121
  • 4
  • 26
  • 46
1
vote
1 answer

JIRA (Greenhopper) How to add Story behindhand (if it's already completed)?

Could you please tip me - how to add the Story(is) behindhand? I work on the project some time already and we decided to start using JIRA. So at the moment I hve some tasks (stories) completed already. And I want to add them in the past to JIRA…
Dmitry Pavlov
  • 25,557
  • 8
  • 92
  • 105
1
vote
2 answers

Prevent anonymous users from seeing agile boards

Is there a way to prevent anonymous user from seeing agile boards in greenhopper? I have checked global permissions but did not find anything that would allow me to limit board visibility. Thank you.
anazimok
  • 1,715
  • 2
  • 20
  • 32
1
vote
1 answer

how do you assign a Jira Issue-Type-Questn under a user story in greenhopper?

I have been using JIRA and Greenhopper to support our Scrum Methodology. Since the User story is the requirement, how then will I be able to track Issue Type "Questions" and link it to a User Story in Greenhopper so that it also appears under the…
Dexter Cato
  • 881
  • 2
  • 8
  • 11
1
vote
1 answer

Getting Burnup Chart For Whole Project

Is there any way to get burnup chart build for the whole project (i.e. across all the versions)? I use Jira with GreenHopper plugin 4.3
0
votes
1 answer

Can Jira/Greenhopper do sub-projects?

Can Jira/Greenhopper do sub-projects? I want to have two main projects, A and B, and then sub-projects A1, A2, A3 and B1, B2, B3. This is critical for maintaining order. I'd like all of the operations teams to be under one operations project, all…