If I have a milestone with 6 open issues and 5 closed ones, what happens to those 6 open issues if I close the milestone?
Asked
Active
Viewed 131 times
1 Answers
2
I've discovered the answer is: nothing
The issues are unaffected. They are still open and still associated with the now-closed milestone.
You can go to Milestones, show closed milestones, and select the milestone you closed. You then see a list of all the open issues associated with it.